Central Coast Council | Ph 03 6429 8900 | Fax 03 6425 1224 | Email: [email protected]st.tas.gov.au
 

PROGRESS UPDATE

PENGUIN FORESHORE REMEDIATION AND UPGRADE PROJECT

Project Home Consultation Activities Site Plan Progress

 

8 April 2021

Construction continues along the Penguin foreshore as part of the Penguin Foreshore Rehabilitation and Upgrade Project. The western section from Penguin Creek along the foreshore adjacent to the Penguin Railway Station is now open for the public to enjoy seeing the coastal erosion protection at their leisure.

It is unfortunate that we have come to the end of March 2021 and the project isn’t quite completed. An additional month is now required to complete construction with the precast stairs adjacent to the Penguin Foreshore Playground causing the biggest delay. This also impacts the construction of the beach ramp at Surf Club Rd as machinery access to the beach is still required.

In the meantime, please enjoy recent drone photos of the Project, as supplied by Tasmanian Consulting Service.


3 March 2021

Stage A of the Penguin Foreshore Remediation and Upgrade Project construction is progressing and all facets of the site are actively busy. The main pathway continues to be built from Penguin Creek including the upgrading of the new beach accesses. Installation of the main verti-block wall has commenced adjacent to the foreshore playground, including a new ramp access. The main rock revetment wall is nearly completed and the kerb and channel have just started along Surf Club Road. Please see aerial pictures below, taken on 27 February.

As an update for Stage B of the Penguin Foreshore Remediation and Upgrade project, the Council has now submitted the complete development application and Planning Permit for Crown Consent for the construction of Stage B to both Property Services (formerly Crown Land) and the Department of State Growth. Once this has been received, the Planning Permit will be submitted and the advertising period will begin for public comment.

The Stage B design is available to download below.

Stage B - Penguin Foreshore Remediation and Upgrade Project- Design

22 January 2021

The Council would like to inform the community that the access ramp pictured below, next to the Penguin Playground, will be closed to allow for the construction of the verti-block wall commencing on Wednesday 27 January until Tuesday 30 March 2021.

Two beach accesses will continue to remain open east of this location along Penguin Beach, including the new beach access at Johnson Beach Rd opposite the newly developed carpark.

The Council regrets any inconvenience caused by this closure and asks for the community’s cooperation in avoiding the construction site during this period.

 


19 November 2020

The Australian Government has committed $6.5m to the Penguin Foreshore project.

As we celebrate the news released on Saturday 14 November of STAGE B in the Penguin Foreshore Remediation and Upgrade Project, let us share with you these images to highlight the first three months of construction.

Please don’t forget to register your interest for the Stage B Information Session. Details are below.

WHAT: The Council are presently ‘at the preliminary design stage’ and as a member of the local community we value your input, ‘do you support the design’?
WHEN: Wednesday 25 November between 6pm and 7pm
WHERE: Dial Park, Dial Park Drive, Penguin

Information Session – Eventbrite Registration

14 November 2020

Coastal erosion is not a static process. With construction well underway to protect Penguin Beach, Surf Club Point Headland at Lions Park continues to erode and Watcombe Beach is not immune either.

Approval was recently received to use remaining Australian Government funding of $3m from what is now known as Stage A, into a Stage B of the Penguin Foreshore Remediation and Upgrade project.  The Council are hosting an Information Session on Wednesday 25 November between 6pm and 7pm at Dial Park to present and receive feedback on Stage B of the Penguin Foreshore Remediation and Upgrade project before the planning process is initiated.

The Information Session will outline:

  • Progress update on Stage A of Penguin Foreshore Remediation and Upgrade project;
  • Why do we have a Stage B of Penguin Foreshore Remediation and Upgrade project; and
  • Synergy between the Perry-Ling Garden Community Survey and Stage B of Penguin Foreshore Remediation and Upgrade project.

What comes from this Information Session, will complement the preliminary concept design and will be used to shape Stage B.

Click on the green button to register for the Stage B – Penguin Foreshore Remediation & Upgrade project – Information Session on Eventbrite: Information Session – Eventbrite Registration


26 October 2020

Delivery of the Verti-blocks to Main Rd will occur from Tuesday 27 October until Wednesday 28 October (over 2 days). The footpath and nearby identified carpark spaces will be closed off during this time. The fence will be moved back, carpark spaces and the footpath will reopen to the public on the afternoon/evening on Wednesday 28 October 2020.

The Council regrets the inconvenience caused by this closure and asks for cooperation in avoiding the construction site during this period.


25 September 2020

The construction phase of the Penguin Foreshore Remediation and Upgrade Project is currently on schedule and you can see from the drone images the progress on the construction of the new sea wall between the 15 September 2020 (top picture below) and 24 September 2020 (lower picture) along Surf Club Road.

15 September 2020

24 September 2020

The construction of the rock wall itself begins today and an average of 4 loads per day will be delivered onsite.

Also, as a courtesy reminder, construction works begin on Monday 28 September on Main Road, Penguin. The construction site will extend out to 8 car parking spaces which will be closed off due to the delivery of required equipment. The fence will be moved back, carpark spaces and the footpath will reopen to the public on the afternoon/evening on Friday 2 October.


1 September 2020

Works on Johnsons Beach Rd, Penguin began on Monday 14 September and will be completed in this area by early to mid November (opened back up to the public). Works will include, removal of existing footpath, garden beds, rock revetment works, new concrete path & also the car parking area. Please note, Johnsons Beach Rd will remain open during this time but please remain cautious if travelling in the area as traffic management will be in place.

The current fencing area along Main Rd (adjacent to the foreshore playground) will become an official work site from Monday 14 September and the footpath will remain open to the public. From Monday 28 September and during the week until Friday 2 October, the footpath and nearby identified carpark spaces will be closed off due to the delivery of required equipment. The fence will be moved back, carpark spaces and the footpath will reopen to the public on the afternoon/evening on Friday 2 October.

Council regrets the inconvenience caused by this closure and asks for cooperation in avoiding the construction site during this period.


26 August 2020

The construction phase of the Penguin Foreshore Remediation and Upgrade Project has commenced with the successful tenderer, Fairbrother Pty Ltd. This project involves the remediation and protection of the beach and escarpment at the Penguin Foreshore.

Unfortunately, due to the complexity and number of construction components along the eastern end of the Penguin foreshore at Lions Parks, Surf Club Road will be closed for the entirety of the construction phase (to 30 March 2021). The Council apologises for any inconvenience caused by this disruption. Other areas of the Penguin foreshore will be closed in smaller sections during construction including parking bays along the northern side of Main Road. The Council will not be shutting down the entirety of the foreshore. We thank the local community for their patience and understanding during this time.

Central Coast Council were successful in obtaining funding for the $6.5m Penguin Foreshore Remediation and Upgrade Project under the Australian Government’s Community Development Grants program.


11 August 2020

TEMPORARY ROAD CLOSURE | SURF CLUB ROAD, PENGUIN

Notice is given that Surf Club Road, Penguin will be closed to the public from Monday 17 August 2020 until Tuesday 30 March 2021 for the construction of the Penguin Foreshore Remediation and Upgrade Project.

The Lions Park public toilets will remain open and can be accessed via Watcombe Beach.

Residents and businesses directly affected have been notified.

For further information, please contact the Council’s Infrastructure Services Department on tel. 6429 8970.

The Council regrets any inconvenience caused by the work.