Project Timeline

Kings Parade Upgrade Project Consultation Activities

Project Timeline

2017

October 

Concept Design Phase Commences

  • Concept Design Options and Feedback Form released
  • First round of Community Engagement Activities commences late October
  • Road use data is collected by the Engineering Team

November

Concept Design Phase Ends

  • Concept Design Options Feedback closes on 26 November
  • Feedback is collated and summarised to inform the Engineering Team

December

Preliminary Design Phase

  • Design work commences on modifying the Concept Design Options, based on the community feedback and technical data, to create new Preliminary Design Options

2018

May

Preliminary Designs Completed

  • Preliminary Design Options and new Feedback Form released
  • Second round of Community Engagement Activities commence

June

Preliminary Design Phase Ends

  • Preliminary Design Options Feedback closes
  • Feedback is collated and summarised to inform the Engineering Group

July

Final Design Phase Commences

  • Design work commences on modifying the Preliminary Design Options based on the community feedback to create a Final Design.

December

Final Design Phase

  • Final design work, including fine tuning access for affected key stakeholders

2019

May

Final Design Phase Ends

  • Final design released to the community for information

June-August

Civil Works Planned

  • After third party checks of the detailed design work, Council expects to advertise Tenders for the project in July 2019 and award the contract for construction in August 2019.

September

Civil Works Underway

  • Civil works are anticipated to commence in September 2019, subject to weather conditions. Construction works will occur for a duration of approximately three months and be substantially completed by December 2019.

Conclusion of Project