Timing

The following table outlines key dates for the Dial Regional Sports Complex Development Project.

Milestone

Key date

Project Launch

29 July 2015

Concept Design developed

23 July 2015

Key user/stakeholder consultation

23 July 2015

Schematic designs developed

July/August 2015

Key user/stakeholder consultation

20 August 2015

Schematic Design community consultation (Display Stands etc.)

20 August – 2 September 2015

Revised Schematic Designs developed

September 2015

Key user/stakeholder consultation

24 September 2015

Final Schematic Designs developed

September/October 2015

Presentation of final Schematic Designs to Council (Council meeting)

19 October 2015

Presentation of final Schematic Designs to community

December 2015

Detailed Design

January 2016 – August/September 2016

Planning Approvals

March 2016 – October 2016

Building Approvals

September/October 2016

Construction commences

Late 2016

NB: A key user or stakeholder for the project are those that currently use Penguin Recreation Ground or Dial Sports Complex.

Find out how to share your views on the Dial Regional Sports Complex designs here.